Introduction: Further to Yamama Cement Company's announcement published on March 12, 2026, regarding the commencement of the trial operation phase of the Third Production Line (formerly Line No. 7), with a daily clinker production capacity of approximately 12.5 thousand tons of clinker, and the financial impact having commenced in the first half of 2026.
Previous Announcement: Yamama Cement Company announced on March 12, 2026, the start of the trial operation phase of the third line (formerly line 7), with a daily production capacity estimated at about 12.5 thousand tons of clinker.
Date of Previous Announcement on Saudi Exchange’s Website: 2026-03-12 Corresponding to 1447-09-23
Hyperlink to the Previous Announcement on the Saudi Exchange Website: Click Here
Latest Developments Of The Announced Event: Commercial operation will commence on July 1, 2026, God willing
Reasons For The Delay on The Date of The Event Previously Announced: N/A
The costs associated with the event, and if they have changed or not with indication of the reasons.: No change has occurred.